OPEXSTUDIO
← All lessons and training aids OPEX learning notes / Standard work and changeover

Manual, walking and machine time

Time elements. Follow the visual, practise a decision, then check your thinking.

Fictional teaching examples and AI-generated illustrations. Proposed changes and goals are not achieved results. Use the written instructions and check local conditions before applying a method.

Download this exact reviewed edition ↗

Teaching view 1 of 2

Manual, walking and machine time

Method exhibit: Load, Automatic cycle, Separate manual task, Wait / observe, Unload.
Original OPEX teaching diagram. Follow the steps below, then try the practice question. View full size ↗

An operator balance chart totals work, but it can hide when automatic processing overlaps manual activity. A combination table puts those activities on a shared time axis. Distinguish hands-on time, walking and automatic machine time, then trace the actual sequence. Check when the person is free, when a machine requires attention and where waiting occurs. Do not add all machine time to labor content or assume that any apparent overlap is feasible. Safe access, sequence and quality requirements remain binding. Use repeated observations and trial the proposed pattern with the operator before revising the method.

Follow the method

  1. Load
  2. Automatic cycle
  3. Separate manual task
  4. Wait / observe
  5. Unload

Read the example carefully

Synthetic timeline: 10 sec load, 20 sec other manual work, 10 sec wait, 10 sec unload; automatic processing overlaps from 10–40 sec.

Manual content is 40 sec; automatic time 30 sec; elapsed cycle 50 sec. Do not add 40 + 30 as if there were no overlap.

Illustrative overlap requires validation of safe access, precedence, task availability and quality; it is not a machine operating instruction.

Teaching view 2 of 2

Explain fifty elapsed seconds without losing any work

A completed resource-time table reconciles 40 manual seconds, 30 automatic seconds, 10 waiting seconds and a 50-second elapsed sequence.
Original OPEX teaching diagram. Follow the steps below, then try the practice question. View full size ↗

Fictional machine-and-bench case: loading takes 10 seconds, the automatic cycle then runs for 30 seconds, a separate manual task takes 20 seconds during that cycle, and unloading takes 10 seconds after it ends. Analyst Theo must explain the supplied 50-second arrangement without double-counting overlap.

Follow the method

  1. Manual work
  2. Automatic process
  3. Operator waiting
  4. Elapsed sequence
  5. Incorrect sum

Read the example carefully

It ends at 45, five seconds after the machine. Unloading is then 45–55 if all access assumptions still hold.

There is no operator wait before unloading; the machine instead waits five seconds. The original 50-second sequence no longer applies.

Apply the method

Thirty automatic seconds are not thirty extra labor seconds

Plot manual work, automatic time and waiting on one timeline, reconcile elapsed and work-content totals, and test whether a proposed overlap is actually permitted.

Fictional machine-and-bench case: loading takes 10 seconds, the automatic cycle then runs for 30 seconds, a separate manual task takes 20 seconds during that cycle, and unloading takes 10 seconds after it ends. Analyst Theo must explain the supplied 50-second arrangement without double-counting overlap.

Role: Process analyst observing with the operator and equipment owner.

Normal condition

No person or machine is assigned incompatible simultaneous work, and access, precedence and quality conditions are respected.

The gap

The draft estimate adds 40 manual seconds and 30 automatic seconds and calls the result a 70-second observed cycle.

  • The overlap is hypothetical and permitted only for this teaching calculation.
  • Task availability, machine access, walking and repeat-cycle feasibility require real verification.
Supplied case inputs
ActivityStart–finishResource
Load0–10 secOperator
Automatic process10–40 secMachine
Separate task10–30 secOperator
Wait30–40 secOperator waits for machine
Unload40–50 secOperator
  1. Draw one common clock

    Theo places each activity on its own resource lane using the same zero point and second scale. Loading ends at 10; only then can the machine start its 30-second interval.

    Why: Independent time bars without a shared clock conceal whether work actually overlaps or violates precedence.

    Evidence: Automatic lane runs from 10 to 40, not from zero to 30.

  2. Place the separate manual task

    Put the 20-second task from 10 to 30 on the operator lane while the machine runs. Leave the operator’s 30–40 interval visible as waiting.

    Why: The manual task overlaps machine processing but not loading or unloading. It cannot be counted twice or assumed possible during prohibited access.

    Evidence: Operator lane: load 10, separate task 20, wait 10, unload 10 seconds.

  3. Reconcile the totals

    Sum manual work as 10 + 20 + 10 = 40 seconds. Automatic time is 30 seconds and elapsed sequence time is 50 seconds. Do not add overlapping resource durations to obtain elapsed time.

    Why: The three totals answer different questions. The ten seconds of waiting remains part of elapsed time but is not manual work content.

    Evidence: Manual 40 sec; automatic 30 sec; waiting 10 sec; elapsed 50 sec.

  4. Challenge the assumptions before improving

    Confirm that the separate task is ready at second 10, that the automatic phase requires no operator attendance, and that required walking or checks have not been omitted.

    Why: A combination table can expose an opportunity, but it cannot make an unsafe or unavailable overlap real.

    Evidence: Validation list names access, attendance, task readiness, walking and repeat-cycle checks.

  5. Record an observed alternative distinctly

    When a trial supplies different times, redraw the intervals from those observations and compare the full sequence. Retain the original supplied model as a prediction.

    Why: A work-content total alone does not show the repeatable output interval, especially where machine and operator cycles interact across units.

    Evidence: Actual trial timings and operating conditions accompany any proposed standard revision.

Completed resource-time reconciliation
QuantityCalculationResult
Manual work10 + 20 + 1040 sec
Automatic process40 minus 1030 sec
Operator waiting40 minus 3010 sec
Elapsed sequence50 minus 050 sec
Incorrect sum40 + 3070 sec double-counts overlap

The separate task takes longer

In a hypothetical variant the separate task takes 35 seconds, starting at second 10.

It ends at 45, five seconds after the machine. Unloading is then 45–55 if all access assumptions still hold.

There is no operator wait before unloading; the machine instead waits five seconds. The original 50-second sequence no longer applies.

Manual content 55 sec; automatic 30 sec; elapsed 55 sec; machine wait 5 sec.

Another machine and task pair

Separate fictional model: load 8 seconds, automatic process 24 seconds after loading, separate task 16 seconds during automatic operation, unload 6 seconds. No walking is included and overlap is declared permitted for the desk exercise.

Changed practice inputs
ActivityDuration
Load8 sec
Automatic24 sec
Separate manual task16 sec
Unload6 sec

Your task

  1. Draw the resource lanes and label all start/finish times.
  2. Calculate manual content, automatic duration, operator waiting and elapsed sequence time.
  3. State two real-world facts that could invalidate the proposed overlap.

Prepare your worksheet

  • Common time origin
  • Resource lane intervals
  • Manual / automatic / waiting totals
  • Elapsed completion
  • Unverified access or task readiness
Reveal the answer and reasoning

Load is 0–8; automatic 8–32; separate task 8–24; waiting 24–32; unload 32–38 seconds.

Manual work is 8 + 16 + 6 = 30 seconds, automatic duration 24, waiting 8 and elapsed sequence 38 seconds.

Operator-attendance requirements, prohibited access, unavailable work or unmeasured travel could change the arrangement.

Worked answer record
MeasureInterval / calculationResult
Manual8 + 16 + 630 sec
Automatic8–3224 sec
Waiting24–328 sec
Elapsed0–3838 sec

Check these interpretations

  • Automatic duration is not always additive labor.
  • A hypothetical overlap does not grant permission to enter a machine area.

Check your work

  • Use one time scale and preserve precedence.
  • Account for waiting without calling it manual work.
  • Name a concrete feasibility check.

Run a practice session

Materials

  • Timeline grid and separate operator/machine markers
  • Original and longer-task cards
  1. Declare the lanes · 4 minutes

    Who is doing each activity?

  2. Build the 50-second sequence · 8 minutes

    Where are the 20 seconds counted in both lanes?

  3. Solve the changed model · 8 minutes

    When can unloading actually begin?

  4. Review reality checks · 5 minutes

    Which condition cannot be proven by arithmetic?

Debrief

  • Ask why the longer task creates machine rather than operator waiting.
  • Do not accept a 70-second elapsed label for the supplied model.

Draw the lanes to scale and check every shared-resource overlap before consulting the answer.

Transfer into the work

Owner: Process engineer with operator and equipment owner

Record: Resource combination table plus observed access, timing and quality conditions

Review: After a controlled timing trial and before standard revision

Evidence: Feasible precedence, complete work content and representative observed sequence timing

Retain the approved method; revise the model from actual evidence and reassess proposed overlap.

Build on reliable methods

Sources and further reading

  • LEI: Standardized Work ↗

    Takt, sequence, standard WIP; chart and combination table have distinct purposes

    Method reference; original OPEX scenario and diagram are synthetic teaching content, not source case results.
Free learning resources

Take the lesson into your team.

Read the lessons online or use these PDFs to prepare, practise and review with your team. No sign-in needed.

Facilitators and team leads

Facilitator guide

Case objectives, demonstration plans, debriefs, common mistakes and application checks across all 81 workplace cases and method lessons.

Download Facilitator guide PDF · 166 pages · 65.1 MB
Learners and improvement teams

Learner workbook

Printable case worksheets, blank observation records and five calculation exercises; answers are separate.

Download Learner workbook PDF · 169 pages · 10.7 MB
Learners after practice and facilitators

Answer key and coaching notes

Reasoned sample responses, worked calculations and coaching guidance; fictional examples are clearly labelled.

Download Answer key and coaching notes PDF · 105 pages · 8.5 MB
Practitioners and facilitators seeking detailed worked methods

Method and application reference

The native method mechanisms and worked applications for all 68 detailed lessons, in a separate bookmarked portrait reference.

Download Method and application reference PDF · 141 pages · 10.2 MB
Self-study learners and workshop groups

Illustrated systems atlas

Five illustrated system chapters: 15 Flare concept maps and 26 original workplace teaching cards, with links to all 81 supporting cases and method lessons.

Download Illustrated systems atlas PDF · 69 pages · 55.8 MB
Connect the methods

Use the next tool for the next question.

  • Element observations
  • Machine boundaries known
Explore all chapters and detailed lessons →